The Proposed Project
The proposed renewable energy project is located approximately 3km southwest of Inistioge and 10km northeast of Mullinavat. The current Study Area comprises lands at Curraghmore, Garrandarragh, Ballykenna, Ballyshane, Ballyvool, Bohilla and Inistioge townlands and measures approximately 294 hectares. The majority of the proposed Study Area is agricultural and forestry land. This area is classified in the Kilkenny City and County Development Plan 2021-2027, as being within an area that is ββopen for considerationββ for wind energy project development, Ministerial Direction is in force on the current County Development Plan. The Study Area is being considered for wind energy potential.
Empower Renewablesβ project selection process initially starts with desk-based screening of the general area which identifies all constraints which are required to establish a feasible Study Area. This includes but is not limited to, buffers off all existing eircode's utilising the most recent eircode data, buffers off all designated environmental areas of importance, national monuments, existing and planned renewable developments, existing grid infrastructure, hydrological features and many more. Once areas of interest are established, we focus on areas with close proximity to grid, and areas designated favourably in the county development plans.
Following this initial screening process, feasibility studies are carried out by independent planning consultants, grid experts and wind analysts to further inform the Study Area suitability.
Based on the results of these initial investigations it is considered that this general area in principle has capacity for a renewable energy project pending further study.
The Study Area is not located within a Natura 2000 site i.e. Special Area of Conservation (SAC) or a Special Protection Area (SPA) nor a Natural Heritage Area (NHA).
The Study Area achieves suitable distances from dwellings in line with government guidelines
The Study Area has suitable grid connection capacity and grid connection options in the wider area
There are suitable turbine component delivery options via national and regional road networks in the wider area
*As recommended by the Office of the Planning Regulator, there is a ministerial direction in place on sections of the Kilkenny City and County Development Plan 2021-2027. For more information see links below.
The Study Area is classified in the Kilkenny County Development Plan 2021-2027, as being within an area that is ββopen for considerationββ for wind energy development*
Project Next Steps
Continue to progress the detailed environmental assessments which will culminate in an Environmental Impact Assessment Report (EIAR). The EIAR is a document that describes the proposed project and assesses its potential effects on the environment and local community. It ensures that any sensitive areas are protected throughout the projectβs design process and forms part of the planning submission to the consenting authority.
Detailed on-site wind measurement has commenced. A meteorological mast has been erected to measure the potential wind speeds available in the area. This met mast is a temporary structure that will be put in place for approximately 18 months, to accurately measure wind speeds within the Study Area, after which time the mast will be removed.
Scoping documents have been issued to numerous statutory and non-statutory organisations, including National Parks and Wildlife, Inland Fisheries Ireland, Telecommunication providers, Transport Infrastructure Ireland, Kilkenny County Council, FΓ‘ilte Ireland, The Aviation Authority plus many more.
Continue to progress detailed grid connection options and turbine component delivery routes.
Bat species monitoring has commenced and will continue over the coming year. Monitoring the bat populations within the project study area will ensure any bat activity and bat habitat is protected during the projectβs design process.
Background noise level monitoring will be carried out over the coming months by installing sound metres at noise sensitive locations. This will form part of the studies to assess the potential impact that noise from the proposed project could have on the surrounding area.
Geotechnical site investigation works have begun. This involves digging small trial pits or drilling narrow boreholes to look at the soil and rock underneath the surface. Engineers will test samples of the soil and rock to understand how strong the ground is and how it drains. This will help to determine the best locations where infrastructure such as turbines and access roads might be placed. These works are temporary, carefully managed and designed to cause as little disturbance as possible.
This project proposal will evolve based on the above-mentioned expert design input across the Study Area as well as input from the local community.
Study Area Map
Project Road Map
Study Area Identified
4th Quarter 2023
Ornithological Studies Commenced
4th Quarter 2023
Landowner Engagement
1st Quarter 2024
Initial Desk-based Assessments
2nd Quarter 2024
Community Consultation Commenced
1st Quarter 2025
Detailed Environmental Assessments Start
1st Quarter 2025
Bat Surveys Commenced
May 2025
Community Project Webinar
June 2025
Noise Monitor Deployment
October 2025
Site Investigations Commenced
October 2025
Door to Door Community Consultation
November 2025
2nd Community Project Webinar
December 2025
1st Community Hall Event
1st Quarter 2026
Planning Application Submission
2nd Quarter 2026